1 (STIP 21) | 2022-01 | Downtown Johnson City Crosswalk Safety Project | Modified to remove $623,197 in CRRSAA-HIP funds (100% Federal) and add $623,197 in STBG-M funds (100% Federal) and move all phases to Fiscal Year 2023. | 6/02/2023 |
10 (STIP 482) | 2017-16 | Traffic Signal for SR 34 (US 11E/ E Jackson Blvd) & Tiger Way | Modification 10 (STIP 482) - Modified to add $104,000 at 100% Federal and $85,000 at 80/20% ($68,000 Federal and $17,000 State) to CONST and move the phase to FY 2025. | 1/17/2025 |
11 (STIP 537) | 2022-01 | Downtown Johnson City Crosswalk Safety Project | Modification 11 (STIP 537) - 4/3/2025 - Modified to move PE-D and both CONST phases, with a total of $925,000, from FY 2023 to FY 2025. | 4/03/2025 |
12 (STIP 538) | 2022-02 | Johnson City Traffic Signal Grouping | Modification 12 (STIP 538) - 4/3/2025 - Moved $2,375,000 in STBG-L funds from FY 2023 to FY 2025 and moved $500,000 from FY 2024 to FY 2026. Added $100,000 to FY 2026. | 4/03/2025 |
13 (STIP 539) | 2023-17 | Old Gray Station Road Section 2 at SR 75 and Traffic Signal | Modification 13 (STIP 539) - 4/3/25 - Modified to add $132,000 Federal in STBG-L funds and $33,000 Local to FY 2026. | 4/03/2025 |
14 (STIP 540) | 2023-18 | ITS Fiber Optic Expansion | Modification 14 (STIP 540) - 4/3/2025 - Modified to move PE-N and PE-D phases from FY 2024 to FY 2025. Moved CONST phase from FY 2024 to FY 2026. Added $100,000 Federal in STBG-L funds and $25,000 in Local funds to PE-N in FY 2025. Reduced PE-D by $20,000 Federal and $5,000 Local and reduced CONST $80,000 Federal and $20,000 Local. | 4/03/2025 |
2 (STIP 86) | 2090595 | Safety - Urban Grouping | Modification 2 (STIP 86) - 8/24/2023 - TDOT is requesting to add $496,500 HSIP-R funding ($446,850 Federal and $49,650 State) to FY 2023. The project total will increase to $666,500. | 8/25/2023 |
3 (STIP 124) | 2023-18 | ITS Fiber Optic Expansion | Modification 3 (STIP 124) - Modified to change the funding source of all phases from STBG-L to CRP, per discussion with TDOT CRP Team. | 10/16/2023 |
4 (STIP 239) | 2017-16 | Traffic Signal for SR 34 (US 11E/ E Jackson Blvd) & Tiger Way | Modification 4 (STIP 239) (2/14/2024) - Modified to break out PE-N and PE-D phases into 80/10/10 shares. Also, CONST was modified from 80/20 to 80/10/10 share. Some phases were moved to FY 2024. | 2/14/2024 |
7 (STIP 283) | 2017-16 | Traffic Signal for SR 34 (US 11E/ E Jackson Blvd) & Tiger Way | Modification 7 (STIP 283) (4/30/2024) - Modified to change the matching funds, currently 10% state and 10% local, to 20% state. | 4/30/2024 |