3 (STIP 124) | Modification 3 (STIP 124) - Modified to change the funding source of all phases from STBG-L to CRP, per discussion with TDOT CRP Team. | 10/16/2023 |
14 (STIP 540) | Modification 14 (STIP 540) - 4/3/2025 - Modified to move PE-N and PE-D phases from FY 2024 to FY 2025. Moved CONST phase from FY 2024 to FY 2026. Added $100,000 Federal in STBG-L funds and $25,000 in Local funds to PE-N in FY 2025. Reduced PE-D by $20,000 Federal and $5,000 Local and reduced CONST $80,000 Federal and $20,000 Local. | 4/03/2025 |