11/6/2019 | AUTHORIZE PE-D | STBG-S | $40,000.00 | (Old SR-34), Bridge over Little Limestone Creek, LM 11.72 (IA) |
11/14/2019 | ADJUST CONST | STBG-S | ($95,200.00) | Intersection at Bugaboo Springs Rd, LM 1.887 |
2/3/2020 | ADJUST CONST | STBG-S | $34,400.00 | From near Green Valley Road to Near Blue Springs Road |
3/10/2020 | AUTHORIZE ROW | STBG-S | $185,600.00 | (Old SR-34), Bridge over Little Limestone Creek, LM 11.72 (IA) |
2/8/2021 | AUTHORIZE CONST | STBG-S | $315,200.00 | From Washington County Line to SR-67 |
2/8/2021 | AUTHORIZE CONST | STBG-S | $200,400.00 | From near Broadway Street to Carter County Line |
2/8/2021 | AUTHORIZE CONST | STBG-S | $240,800.00 | From near I-26 to near Milligan Highway |
2/8/2021 | AUTHORIZE CONST | STBG-S | $293,280.00 | From near SR-359 to near SR-91 |
6/23/2021 | ADJUST CONST | STBG-S | $14,800.00 | From near I-26 to near Milligan Highway |
6/25/2021 | ADJUST CONST | STBG-S | $17,680.00 | From near Broadway Street to Carter County Line |
6/25/2021 | ADJUST CONST | STBG-S | $29,920.00 | From Washington County Line to SR-67 |
6/25/2021 | ADJUST CONST | STBG-S | $52,320.00 | From near SR-359 to near SR-91 |
11/8/2022 | CLOSE PROJECT | STBG-S | ($21,326.11) | From near Broadway Street to Carter County Line |
11/8/2022 | CLOSE PROJECT | STBG-S | ($2,324.36) | From Washington County Line to SR-67 |
12/23/2022 | AUTHORIZE CONST | STBG-S | $1,016,736.00 | From near SR-37 to near Green Valley Lane |
3/1/2023 | CLOSE PROJECT | STBG-S | $18,241.54 | From near I-26 to near Milligan Highway |
3/1/2023 | AUTHORIZE CONST | STBG-S | $1,716,444.00 | From near Nolichuckey River to near Ridgecrest Road |
3/1/2023 | CLOSE PROJECT | STBG-S | $82,254.34 | From near SR-359 to near SR-91 |
TOTAL | | | $4,139,225.41 | |