9 | Modified for TDOT to replace $2,665,549 of the STBG funds for CONST in FY 2020 with HPP funds. The final Construction phase or total project amount has not changed. | 8/04/2020 |
22 | Modified because TDOT is adding $1,500,000 of STBG funds in FY 2022 for CONST. Total project cost is increased to $12,983,549. | 12/02/2021 |
23 | Modified because TDOT is adding a line for ROW in FY 2022 in the amount of $34,451 of STBG funds to account for an overage. $3,429,000 of STBG funds are added to CONST in FY 2022 based on the latest construction bid. Total project cost is increased to $16,447,000. | 1/07/2022 |