TIP Project #2010010: State Route (SR) 91 Extension

Resurface and restripe existing 5-lane, reconstruct 4-lane to 5-lane, add curb and gutter section, add sidewalk section, reconfigure intersection of North Roan St and East Elk Ave.

M Reconstruction Regional Plan ID: E+C, page 4-6
TDOT TDOT PIN: 043975.01
Carter County Total Cost: $16,447,000.00
SR 91 Total Programmed: $10,863,451.00
SR091 (Elk Ave) from near SR-67 (US-321) to near SR-37 (US-19E) (IA) Federal Share: $8,690,759.00
4.00 miles Federal Obligation*: $11,708,543.54
Attainment Unobligated Balance: ($3,017,784.54)
* Obligations during current TIP period only.

Programmed Funds

Fiscal YearPhaseFunding SourceTotal FundsFederal FundsState FundsLocal Funds
2020ConstructionHPP$2,665,549.00$2,132,439.00$533,110.00$0.00
2020ConstructionSTBG-S$3,234,451.00$2,587,560.00$646,891.00$0.00
2022ConstructionSTBG-S$4,929,000.00$3,943,200.00$985,800.00$0.00
2022Right-of-WaySTBG-S$34,451.00$27,560.00$6,891.00$0.00
TOTAL  $10,863,451.00$8,690,759.00$2,172,692.00$0.00

Construction Reserve Funds

There is no reserve funding information for this TIP Project.

Obligated Funds

Obligation DatePhaseFunding SourceFederal FundsNotes
6/20/2018AUTHORIZE ROWHPP$2,334,400.00(Elizabethton Connector), From SR-67 (US-321) to SR-37 (US-19E) (IA)
5/17/2021ADJUST ROW; AUTHORIZE CONSTHPP$2,132,439.54From SR-67 (US-321) to SR-37 (US-19E)
5/17/2021ADJUST ROW; AUTHORIZE CONSTSTBG-S$3,450,480.00From SR-67 (US-321) to SR-37 (US-19E)
2/3/2022ADJUST CONSTSTBG-S$3,791,224.00From SR-67 (US-321) to SR-37 (US-19E)
TOTAL  $11,708,543.54 

Project Images and Videos

SR 91 Extension

Project Documents and Links

There are no documents or links for this TIP Project.

Project Notes

NotePosted On
The total project cost also includes $1,500,000 of PE funds obligated in 2006. Previous ROW funds obligated in 2002. Funding provided by HPP# TN024 in TEA-21-Sec. 1602.2/04/2019

Project Amendments

There are no amendments for this TIP Project.

Administrative Modifications

Adjustment #ActionMPO Approval
9Modified for TDOT to replace $2,665,549 of the STBG funds for CONST in FY 2020 with HPP funds. The final Construction phase or total project amount has not changed. 8/04/2020
22Modified because TDOT is adding $1,500,000 of STBG funds in FY 2022 for CONST. Total project cost is increased to $12,983,549. 12/02/2021
23Modified because TDOT is adding a line for ROW in FY 2022 in the amount of $34,451 of STBG funds to account for an overage. $3,429,000 of STBG funds are added to CONST in FY 2022 based on the latest construction bid. Total project cost is increased to $16,447,000. 1/07/2022

Submit a Comment

The Johnson City Metropolitan Planning Organization welcomes your feedback. Please enter your comment below and click Submit. While we review all comments carefully, we are not able to respond to every comment.

Your name:*  
Phone #:  
Email address:  

Your comment:

Please limit your comment to 2,000 characters.