TIP Project #90115: I-26 Exit 17

Interchange Modification

M Interstate Maintenance Regional Plan ID: E+C, page 4-6
TDOT TDOT PIN: 112456.00
Washington County Total Cost: $17,500,000.00
I-26 Total Programmed: $16,700,000.00
Interchange at SR-354 (Exit 17) (IA) Federal Share: $15,030,000.00
0.80 miles Federal Obligation*: $11,999,169.00
Attainment Unobligated Balance: $3,030,831.00
* Obligations during current TIP period only.

Programmed Funds

Fiscal YearPhaseFunding SourceTotal FundsFederal FundsState FundsLocal Funds
2017PE- DesignNHPP$200,000.00$180,000.00$20,000.00$0.00
2017Right-of-WayNHPP$500,000.00$450,000.00$50,000.00$0.00
2019ConstructionNHPP$16,000,000.00$14,400,000.00$1,600,000.00$0.00
TOTAL  $16,700,000.00$15,030,000.00$1,670,000.00$0.00

Construction Reserve Funds

There is no reserve funding information for this TIP Project.

Obligated Funds

Obligation DatePhaseFunding SourceFederal FundsNotes
2/25/2019AUTHORIZE CONSTNHPP$12,924,450.00Interchange at SR-354(Exit 17) (IA)
5/14/2019ADJUST PE-D & CONSTNHPP($925,281.00)Interchange at SR-354(Exit 17) (IA)
TOTAL  $11,999,169.00 

Project Images and Videos

I-26 Exit 17

Project Documents and Links

There are no documents or links for this TIP Project.

Project Notes

NotePosted On
Preliminary Engineering - NEPA Phase in previous TIP.10/06/2016

Project Amendments

Amendment #ActionMPO ApprovalTDOT ApprovalUS DOT Approval
4Amended to add Construction Phase to FY 2019 for a total of $13,400,000. Also, IA (IMPROVE Act) is added to the terminus.8/23/20189/05/2018 

Administrative Modifications

Adjustment #ActionMPO Approval
23Adjusted to increase CONST in FY 2019 by $2,600,000, from $13,400,000 to $16,000,000. 2/14/2019

Submit a Comment

The Johnson City Metropolitan Planning Organization welcomes your feedback. Please enter your comment below and click Submit. While we review all comments carefully, we are not able to respond to every comment.

Your name:*  
Phone #:  
Email address:  

Your comment:

Please limit your comment to 2,000 characters.