TIP Project #2010-05: Traffic Circle at Mountainview Road

Installation of traffic circle at the intersection of Mountainview Road and Browns Mill Road.

M Intersection Regional Plan ID: E+C, page 5-5
Johnson City TDOT PIN: 114592.00
Washington County Total Cost: $1,663,000.00
Mountainview Rd and Browns Mill Rd Total Programmed: $1,510,000.00
Intersection of Mountainview Rd and Browns Mill Rd Federal Share: $1,510,000.00
0.00 miles Federal Obligation*: $2,809,600.00
Attainment Unobligated Balance: ($1,299,600.00)
* Obligations during current TIP period only.

Programmed Funds

Fiscal YearPhaseFunding SourceTotal FundsFederal FundsState FundsLocal Funds
2017ConstructionSTBG-Local$1,510,000.00$1,510,000.00$0.00$0.00
TOTAL  $1,510,000.00$1,510,000.00$0.00$0.00

Construction Reserve Funds

There is no reserve funding information for this TIP Project.

Obligated Funds

Obligation DatePhaseFunding SourceFederal FundsNotes
2/27/2017ADJUST CONSTSTBG-Local$209,600.00 
9/6/2016AUTHORIZE CONSTSTBG-Local$1,300,000.00 
9/6/2016AUTHORIZE CONSTSTBG-Local$1,300,000.00 
TOTAL  $2,809,600.00 

Project Images and Videos

Traffic Circle Mountainview Rd

Project Documents and Links

There are no documents or links for this TIP Project.

Project Notes

NotePosted On
Preliminary Engineering - NEPA/Design and Right-of-Way Phases in previous TIPs.10/06/2016

Project Amendments

There are no amendments for this TIP Project.

Administrative Modifications

Adjustment #ActionMPO Approval
4Adjusted FY 2017 Construction funds to add $10,000.2/13/2017

Submit a Comment

The Johnson City Metropolitan Planning Organization welcomes your feedback. Please enter your comment below and click Submit. While we review all comments carefully, we are not able to respond to every comment.

Your name:*  
Phone #:  
Email address:  

Your comment:

Please limit your comment to 2,000 characters.